Do you charge VAT on labour at all?
Only if you're VAT-registered. You have to register once your taxable turnover goes over £90,000 in any rolling 12 months, or you expect it to in the next 30 days alone (the threshold since 1 April 2024). Below that, you can register voluntarily, and if you don't, there's no VAT on your invoices.
Once you're registered, 20% is where you start. In Notice 708's words: "The construction of a new building and work to an existing building is normally standard-rated."
The three rates side by side
| The job | Rate | What has to be true | Notice 708 |
| Repairs, maintenance, refits, extensions and decorating on an existing building | 20% | Nothing. It's the default | Paragraph 2.1 |
| Building a new house or flats | 0% | Built from scratch, designed as homes that can be used and sold separately, with planning consent, and your work's done before completion | Section 3 |
| Turning a non-residential building into homes, or changing the number of homes in a building | 5% | A qualifying conversion, with planning consent or building control where the work needs them | Section 7 |
| Renovating or altering a home | 5% | Nobody's lived in it during the 2 years immediately before your work starts | Section 8 |
What counts as a new build, and what doesn't get the 0%
On a new home, zero-rating covers your work "in the course of the construction" of the building, from groundworks to decorating, and the building materials you fit while you're at it. That includes things a builder would normally fit in a house, like fitted kitchen units, boilers and floor tiles (section 13).
It's zero-rated, not exempt, and the difference is money. A zero-rated supply is still a taxable one, so you reclaim the VAT on your materials and other job costs as normal (paragraph 2.3.1). If the work were exempt, you couldn't.
That's why there's no such thing as a new build VAT exemption list. What there is, though, is a list of things that stay at 20% even on a zero-rated site:
- architects, surveyors, consultants and supervisors (paragraph 3.4.1)
- hire of plant without an operator, scaffolding, security fencing or mobile offices, though putting up and taking down the scaffolding can still be 0% (paragraph 3.4.2)
- carpets and underlay, and fitted furniture other than kitchen units, with a narrow exception for basic built-in wardrobes (paragraphs 13.5 and 13.7)
- plug-in appliances, and hobs and ovens (paragraphs 13.3 and 13.6)
- work after the building's complete, including fixing someone else's snags (paragraphs 3.3.2 and 3.3.3)
Watch mixed buildings. Build a shop with a flat above and only the flat's zero-rated, so your price gets split fairly (paragraph 3.5.1).
When is building work 5%?
You've got two routes. The first is a conversion: turning an office block or a barn into a house or flats, or changing how many homes a building holds, like splitting a house into flats (section 7).
The second is a home that's stood empty. If nobody's lived in it during the 2 years immediately before your work starts, your repairs, redecoration, double glazing and even an extension done as part of the renovation are 5% (section 8). Squatters, property guardians and storage use don't count as living there, but a second home used now and then does. A letter from the council's Empty Property Officer is enough proof on its own (paragraph 8.3.2).
Inside a 5% job, some things still go on at 20%: carpets, fitted bedroom furniture, scaffolding, hired kit, landscaping and professional fees (paragraphs 7.6 and 8.4). If you don't split the bill, none of it gets the 5%.
Does a subcontractor charge the same rate as the main contractor?
Normally, yes. Notice 708 says subcontractors can zero-rate or reduce-rate "according to the building being constructed or worked on" (paragraph 2.1.3). So a labour-only bricklayer on a new house charges 0%, and a plasterer on a barn conversion charges 5%, the same as the builder above them. There are three exceptions you can't follow the main contractor on:
- Certificated buildings. A care home, student halls or a charity's village hall gets its relief through a certificate the customer gives the main contractor. As a subcontractor you can't use it, so you always charge 20% (paragraph 17.4).
- Housing association conversions. The main contractor can zero-rate, but your work isn't made to the housing association, so you don't get the 0% (paragraph 6.2.3).
- A long-empty home the new owner's already living in. The builder working for the owner direct can charge 5%; a subcontractor charges 20% (paragraph 8.3.4). If the house is still empty when the work starts, you follow the builder's 5%.
Whatever the rate, the reverse charge is a separate question, and the reverse charge checker answers it for a single job.
Four worked invoices
Example figures, and every job assumes you're VAT-registered.
| The job | Rate | Labour | Materials | Net | VAT | Invoice total |
| A. Kitchen refit in a lived-in house, for the homeowner | 20% | £2,400 | £1,600 | £4,000 | £800 | £4,800 |
| B. Supply-and-fit brickwork on a new house, for the housebuilder | 0% | £6,000 | £2,000 | £8,000 | £0 | £8,000 |
| C. Plastering a house empty for 3 years, for the owner | 5% | £3,000 | £500 | £3,500 | £175 | £3,675 |
| D. Rewiring a lived-in house, as subcontractor to a builder | 20%, reverse charge | £2,000 | £1,000 | £3,000 | £600, paid over by the builder | £3,000 |
Job A. The 20% goes on the whole £4,000, not just the labour: £480 on the labour and £320 on the materials. You paid £320 VAT on those materials at the merchant and reclaim it, so the materials VAT washes through and the £480 on your labour is what's left.
Job B. Nothing goes on the invoice, but you still reclaim the £400 VAT you paid on £2,000 of bricks and blocks. Job C is 5% of £3,500, so £175. Carpet laid on the same job would be 20%, as it isn't a building material.
Job D is where the reverse charge bites. All five conditions are met: rewiring's a CIS service, you're both VAT-registered, the builder reports the payment under CIS, the builder isn't the end user because it's selling the work on, and the work's at 20%. So you don't charge the £600. Your invoice shows £3,000 with a reverse charge note, and the builder pays the £600 over on its own return. The rate hasn't changed. How to invoice under the reverse charge has the exact wording and what changes on your return.
The builder's also your contractor under CIS, so if you're registered it'll deduct 20% from the labour only, never the materials. That's £400 on job D (you're paid £2,600) and £1,200 on job B (you're paid £6,800).
The reverse charge works the same way at 5%: do job C as a subcontractor to a registered builder and you'd show the £175 for the builder to pay over. It never touches 0% work, so job B stays an ordinary zero-rated invoice. And if the reverse charge part of a supply is 5% or less of the contract's value, and you and the builder agree that at the start, you ignore it and use normal VAT rules for the lot. It's judged on the contract values, not invoice by invoice. If you're the builder receiving these invoices, the contractor's side of the reverse charge covers end-user notices.
Getting the rate right before the invoice goes out
Three questions settle it, and they're easier to answer when you price the job than after the invoice has gone. Is the building new, being converted, or empty for 2 years? Has the customer given a certificate? And who are you working for: the owner, a builder, or a developer selling the homes on? We'll go through them with you and tell you the rate, whether the reverse charge applies and how it lands on your VAT return. Here's what we do on VAT and the reverse charge. We reply within 24 hours.